SECURITIES AND EXCHANGE COMMISSION

                     WASHINGTON, D.C.  20549


                       ___________________


                            Form 8-K

                         Current Report

                Pursuant to Section 13 or 15(d) of
                the Securities Exchange Act of 1934


                  Date of Report:  October 1, 1996


            CONSOLIDATED EDISON COMPANY OF NEW YORK, INC.
         (Exact name of registrant as specified in charter)



        New York              1-1217              13-5009340
       (State of            (Commission        (I.R.S. Employer
     incorporation)         File Number)      Identification No.)



               4 Irving Place, New York, NY  10003
            (Address of principal executive offices)


        Registrant's telephone number:  (212) 460-4600

















                         - 2 -


                INFORMATION TO BE INCLUDED IN THE REPORT


ITEM 5.  OTHER EVENTS

     On October 1, 1996, Con Edison provided its plan ("Con
Edison's Plan") in response to the order of the New York State
Public Service Commission ("PSC"), issued May 20, 1996 in its
"Competitive Opportunities" proceeding (the "Order"). Con
Edison's Plan, which is described in more detail below, proposes
a transition to a competitive electricity market (with retail
access for Con Edison customers by 2003, if feasible), a five-
year "rate freeze" to take effect April 1997 (beginning with the
last year of Con Edison's current electric rate agreement), full
recovery from customers of all prior utility investments and
commitments, including potential "strandable costs", a corporate
reorganization into a holding company structure, and tax and
regulatory reform.

     On September 17, 1996, the New York State Energy
Association, on behalf of Con Edison and the other New York State
investor owned electric utilities, commenced a proceeding in the
Supreme Court of the State of New York, Albany County, to
challenge the Order and, among other things, the authority of the
PSC to deny recovery of prudent investment, order divestiture or
order retail access.  This proceeding was instituted prior to the
expiration of the four-month statute of limitations applicable to
judicial review of the Order.

     Con Edison, without prejudice to its rights in connection
with the proceeding challenging the Order, intends to continue
its collaborative efforts with the PSC staff and other interested
parties and has set year-end 1996 as a goal for reaching
agreement on Con Edison's Plan. If agreement cannot be reached,
at some point it might become necessary for the PSC to institute
formal hearings on matters under its purview.  In addition to PSC
approval, as discussed below, certain other approvals and the
enactment of certain legislation are required.

     Con Edison's Plan could change materially before it becomes
effective.  It is not possible to predict the outcome of the
PSC's Competitive Opportunities proceeding or its impact on Con
Edison.  However, the outcome could potentially have a material
adverse effect on Con Edison, its financial condition and results
of operations.



                         - 3 -


THE PSC ORDER

     The Order endorsed a fundamental restructuring of the
electric utility industry in New York State, based on competition
in the generation and energy services sectors of the industry. 
The PSC stated that it expected wholesale competition to begin in
early 1997, and retail competition to begin in early 1998. The
stated goals of the PSC are (1) lowering rates for consumers; (2)
increasing customer choice as to both suppliers and types and
levels of service; (3) continuing reliability of service; (4)
continuing public interest programs such as energy efficiency and
environmental protection; (5) mitigating concentrations of market
power; and (6) continuing customer protections and the obligation
to serve. To implement this restructuring, the PSC, in the Order,
envisioned the establishment of (i) an "Independent System
Operator" that would control and operate the electric
transmission facilities in the State as an integrated system, and
(ii) a market exchange that would establish visible spot market
prices.

     To address market power concerns, the PSC indicates the
separation of (a) generation, (b) transmission and distribution
and (c) energy services activities, is "encouraged."  The PSC
notes that such separation could be achieved functionally, by
maintaining separate books and records; structurally, by placing
each activity in a separate subsidiary or affiliate; or by
divestiture, through a sale or spinoff. The Order states: "We
strongly encourage divestiture, particularly of generation
assets, but do not require it immediately." Similarly, the Order
notes: "While divestiture of energy service company operations is
encouraged, for now we will allow utilities to continue to
provide energy services to their customers either directly or
through an affiliate."

     The PSC recognizes in its Order that certain costs incurred
by utilities in the past under traditional regulation could
become unrecoverable in the transition from regulation to a
competitive market for electricity. The PSC rejected the argument
made by the investor-owned utilities, that they are legally
entitled to recover (and earn a return on) all prudent costs
incurred in the provision of services under past regulation. The
PSC indicated that utilities are entitled only to "just and
reasonable" rates, and that "while 'just and reasonable' rates
must reflect a reasonable balancing of ratepayer and shareholder
interests, they may or may not include stranded investment." As a
general policy, the PSC stated that "utilities should have a
reasonable opportunity to seek recovery of strandable costs
consistent with the goals of lowering rates, fostering economic
development, increasing customer choices, and maintaining
reliable service."

                         - 4 -


TRANSITION TO COMPETITION

System Security Operator and Power Exchange

     Con Edison's Plan supports the establishment of a New York
State "System Security Operator" ("SSO"), which would perform
some of the functions of the "Independent System Operator"
envisioned by the PSC, to ensure the reliability of the bulk
power system by establishing and enforcing the rules and
procedures which all market participants must follow.  Con
Edison's Plan also supports the establishment of a power exchange
- - a voluntary, commercial market with visible pricing for
electricity.  Con Edison is working with the other New York
utilities and other parties to develop the SSO and power
exchange, and expects that prior to the end of 1996 a required
submission for approval to establish the SSO and power exchange
will be made to the Federal Energy Regulatory Commission
("FERC").

Wholesale Competition

     Con Edison has lowered its costs of electricity with short-
term purchases in the increasingly competitive wholesale market.
Con Edison's Plan calls for the establishment of the SSO and a
power exchange and increased wholesale competition in 1997.  A
capacity market is expected to be established in 1998, after the
SSO and power exchange are functioning fully.  Generators of
electricity could submit bids to sell energy to, and load serving
entities could submit bids to buy energy from, the power exchange
which, based on information from the SSO and other information
available to it, would select the most economical bids to
schedule delivery of electricity for the following day.  The
energy market would use a "locational-based marginal pricing"
mechanism which takes into account transmission limitations. 
Generators will have the opportunity to enter into bilateral
contracts for electricity, which also would be scheduled through
the SSO.  Con Edison's Plan proposes that all load serving
entities (including power marketers and energy service companies)
be required to demonstrate that they have capacity resources
consistent with their customer load, and that either a
locational-based electric capacity market be developed or that
there be a specific requirement that a substantial portion of
such capacity resources be located where it will be used.


                         - 5 -


Retail Competition

     Con Edison's Plan proposes a 100 MW retail access energy
pilot program for the period April 1, 1998 through March 31, 1999
and an energy and capacity program beginning in 1999.  The energy
and capacity retail access program would be expanded in annual
increments.  Con Edison expects that all Con Edison customers
desiring retail access could participate in the program by 2003. 
If customer interest is greater than expected, Con Edison would
review the retail access program and ascertain whether the
schedule could be accelerated to accommodate the greater-than-
anticipated participation, and the schedule would be modified to
reflect this greater interest if feasible.  In the event such
modifications were not feasible, Con Edison expects that all
customers would have retail access by 2006.  Con Edison proposes
that the status of the transition be reviewed in 2001, near the
end of the rate freeze. (See "FIVE-YEAR RATE FREEZE", below.)

     In general, Con Edison's delivery rates for retail access
customers will equal the rate applicable to other comparable Con
Edison customers less the market value of the energy and capacity
being supplied for the customer.  By this pricing methodology,
Con Edison will recover from retail access customers the same
"system" costs as would be allocable to Con Edison's other
customers, including any potential "strandable costs." (See
"RECOVERY OF STRANDABLE COSTS", below).

     Con Edison's generation and transmission system was designed
as a vertically-integrated system to achieve reliability
objectives at lowest cost which in some cases required building
local generation plants instead of installing transmission
facilities.  As a result, a substantial portion of Con Edison's
service area constitutes one or more "load pockets" where the
transmission capacity supplying the area is less than the demand
in the area during certain periods.  Con Edison expects to work
with interested parties during the transition to retail access to
establish a competitive in-City generation market.  This process
will include exploring:  the supply of new capacity by non-
regulated generators; the sale of blocks of energy and capacity
into the wholesale market; divestiture of Con Edison fossil-
fueled plants; and buyouts or restructuring of non-utility
generator ("NUG") contracts where the related capacity could be
used to supply directly the retail market.


                         - 6 -


FIVE-YEAR RATE FREEZE

Final Year of Current Agreement

     Con Edison is filing for an increase to its electric rates
to become effective April 1, 1997 for the third rate year of the
current rate agreement.  Under the terms of the agreement, the
estimated increased revenue requirement, which could vary based
on data available by early 1997, is $87 million (an increase of
approximately 1.6%). Con Edison will be reviewing measures to
mitigate this increase.

     Con Edison is also proposing that provision be made for
refund to or recovery from customers of differences between
actual and projected amounts for certain expenses that may be
deferred, and incentives (or penalties) that may be accrued, for
the third rate year.  See "1995 Electric Rate Agreement" in Item
7 of Con Edison's Annual Report on Form 10-K for the fiscal year
ended December 31, 1995.

Rate Freeze 

    Con Edison's Plan would provide for base rates to remain
unchanged for the five-year period from April 1, 1997 through
March 31, 2002, with limited exceptions for changes after April
1, 1998, including for changes in laws; property tax increases;
greater than 4% annual inflation; and increased financing costs
should refunding of Con Edison's tax-exempt debt become necessary
as a result of the restructuring.  Con Edison's Plan also
includes provisions for:

     -  elimination of reconciliations or "true-ups" of amounts
        included in base rates with actual costs for pension and
        other post-employment benefits, NUG capacity charges and
        Enlightened Energy program expenses;

     -  elimination of provisions such as those in Con Edison's
        current rate agreement for rate incentives (or
        penalties), the electric rate adjustment and related
        revenue per customer revenue mechanisms (the so-called
        "modified ERAM"), and earnings sharing; and

     -  implementation of a systems benefit charge for recovery
        of environmental costs, energy efficiency programs,
        research and development and the costs of other public
        policy initiatives.


                         - 7 -


RECOVERY OF PRIOR INVESTMENTS AND COMMITMENTS

     Potential "strandable costs" for Con Edison are those prior
utility investments and commitments prudently incurred by Con
Edison to provide safe and reliable service to its customers that
may not be recoverable in a competitive retail electric market. 
Con Edison estimates that, on a present value basis, its
strandable costs could be between $4.7 billion and $6.2 billion,
including an estimated $650 million relating to its fossil-power
plants; $1.1 billion relating to its nuclear generating
operations (including decommissioning costs) and $3 billion to
$4.5 billion relating to capacity charges under Con Edison's
contracts with NUG's.  (These estimates are forward-looking
statements. Actual stranded costs might differ materially from
these estimates because of factors affecting the future market
price of capacity (such as weather variations, changes in energy
usage patterns or economic conditions, technological
developments, or installation of new, or retirement of existing,
generation or transmission capacity), changes in laws or
regulations, and other presently unknown or unforeseen factors.)

     Con Edison's Plan provides for accelerating depreciation of
its fossil-power plants to reduce the net book value of the
plants to their estimated market value by 2002.  Con Edison
expects that the rate freeze (which, in general, would continue
to permit recovery in rates of current cost levels) would enable
Con Edison to offset the effect on earnings of the increased
depreciation expense.  (See "FIVE-YEAR RATE FREEZE", above.) All
costs for nuclear generating operations and charges under NUG
contracts would continue to be reflected in Con Edison's rates
and recovered from all Con Edison customers, including retail
access customers. (See "TRANSITION TO COMPETITION - Retail
Competition", above)

     Con Edison supports enactment of legislation in New York
State, comparable to legislation recently enacted in other
states, that would facilitate mitigation of the above-market
costs for electricity under Con Edison's contracts with NUG's by
providing for cost-effective securitization of the mitigation
costs.  If such legislation were enacted, Con Edison, subject to
satisfying any conditions of the legislation, could fund a
payment made to terminate or modify a NUG contract by
transferring its right to recover the payment from its customers
to a financing entity that would in return remit to Con Edison
the proceeds of debt issued by the financing entity.  The debt,
which would be non-recourse to Con Edison, would be secured by,
and repaid from, the future customer payments.  This legislation
could also be used to mitigate other costs.

                         - 8 -


CORPORATE REORGANIZATION

     Con Edison's Plan proposes reorganizing Con Edison by
creating a holding company and conducting Con Edison's regulated
and competitive businesses through separate subsidiaries of the
holding company.  The reorganization is subject to approval,
including by Con Edison's shareholders, the PSC and the FERC.

     Under Con Edison's Plan, Con Edison, the existing publicly-
held corporation, will become a wholly-owned subsidiary of the
holding company pursuant to a binding share exchange in which the
outstanding common stock of Con Edison is exchanged for the
common stock of the holding company. Initially, this regulated
subsidiary will own all Con Edison's existing generating plants. 
In addition, Con Edison's Plan provides for the holding company
to initially have energy supply, energy services and new ventures
subsidiaries.  The energy supply subsidiary is expected to become
an unregulated owner and operator of electric generating plants,
possibly including some existing Con Edison fossil-power plants. 
(It is expected that by the end of the transition to retail
access for all Con Edison customers, Con Edison's fossil-power
plants will be sold to third parties, transferred to the energy
supply subsidiary or retired.)  The energy services subsidiary is
expected to engage in both wholesale and retail sales and trading
of electric energy and capacity and gas and to become a full-
service provider of other energy services.  (It is expected that
Con Edison's existing gas marketing subsidiary, ProMark Energy,
Inc., will be transferred to the holding company to become the
energy services company.)  The new ventures subsidiary or its
subsidiaries will invest in competitive businesses which
initially are expected to include investments in energy
infrastructure development projects and the marketing of
technical services.

TAX AND REGULATORY REFORM

     Tax and regulatory reform is an essential part of Con
Edison's Plan and will require legislation to be enacted in New
York State to provide fairness to all competitors so that Con
Edison and its competitive businesses can compete without unfair
burdens of regulation and taxes.  The reforms Con Edison
recommends include the substitution of a net income tax for the
New York State and municipal gross receipt taxes (which currently
apply to Con Edison but would not, for the most part, apply to
out-of-state competitors); the elimination, as retail access is
provided, of Con Edison's obligation to plan for and provide
energy and capacity for its service area; and the elimination of
the PSC's authority to regulate the generation of electricity.


                       - 9 -


                           SIGNATURE





     Pursuant to the requirements of the Securities Exchange Act
of 1934, the registrant has duly caused this report to be signed
on its behalf by the undersigned hereunto duly authorized.

                                CONSOLIDATED EDISON COMPANY
                                  OF NEW YORK, INC.              



                                By: JOAN S. FREILICH
                                    JOAN S. FREILICH
                                    Senior Vice President and
                                      Chief Financial Officer


DATE:  October 1, 1996